The EUChinaGRID project officially ended on 31 March 2008, after 27 months of activity and a number of goals achieved. The following is the full list of Periodic activity Reports delivered to EC during the project lifetime. Activity reports contain confidential information and require authorization to be accessed. If you don't have your credentials and you are entitled to access the documents, please .
Name | Activity period | Status | Due on |
---|---|---|---|
Q1 - Quartely report #1 | 01/01 to 31/03/2006 | delivered | 12/05/2006 |
Q2- Quartely report #2 | 01/04 to 30/06/2006 | delivered | 09/08/2006 |
Q3- Quartely report #3 | 01/07 to 30/09/2006 | delivered | 16/11/2006 |
Y1- Year report #1 | 01/01 to 31/12/2006 | delivered | 13/02/2007 |
Q5 - Quartely report #5 | 01/01 to 31/03/2007 | delivered | 16/05/2007 |
Q6- Quartely report #6 | 01/04 to 30/06/2007 | delivered | 09/08/2007 |
Q7- Quartely report #7 | 01/07 to 30/09/2007 | delivered | 01/11/2007 |
Q8 - Quarterly report #8 | 01/10 to 31/12/2007 | delivered | 15/02/2008 |
Y2 - Yearly report #2 | 01/01 to 31/03/2008 | delivered | 15/02/2008 |
HIGHLIGHTS
The EUChinaGRID project officially ended on 31 March 2008, after 27 months of activity and a number of goals achieved.
However, the project consortium is planning further collaboration activities for the next few months.